The Swiss Contribution to enlargement aims to finance a broad variety of projects. The PPF provided the necessary financial assistance to enable Executing Agencies to submit high quality project proposals. This was especially important in the case of complex projects.

Country/region Topic Period Budget
Slovenia
Project Preparation Facility
01.08.2008 - 14.04.2012
CHF 300'000
Background

Poorer regions do not have the financial means to prepare a good Final Project Proposal. Likewise, complex projects demand a costly preparation.

Objectives

The goal of the PPF was to ensure the efficient preparation of good quality Final Project Proposals.

Target groups

Executing Agencies / Intermediate Bodies

Activities

The PPF could be used for mandates of competent external experts for preparing studies, e.g. feasibility studies, environmental impact assessments, and/or translations into English.

Results

Achieved results:  

The Project Preparation has contributed to the preparation of Swiss funded projects. It allowed the partners to elaborate high-quality project documentation. With this, the Project Preparation Facility played a major role in enabling Switzerland to approve all the projects and to fully commit all the available funds by June 2012.


Directorate/federal office responsible SECO
Credit area Swiss Contribution to the enlarged EU
Project partners Contract partner
  • National Coordination Unit
  • Slovenian Government Office for European Affairs

Implementing partner
Several Slovenian Executing Agencies

Budget Current phase Swiss budget CHF   300'000 Swiss disbursement to date CHF   164'714
Project phases

Phase 1 01.08.2008 - 14.04.2012   (Completed)