Updating flood protection plans upper Tisza
The project’s goal is to protect the population of the upper Tisza river by taking appropriate measures against floods. To achieve this, topographical and biomass data is acquired by aerial scanning before being transformed into a relief model of the embankments of the Tisza river. This model serves as a basis for effective measures in case of floods. Tematica / Settore d'intervento
Sicurezza, stabilità e sostegno alle riforme
Gestione delle catastrofi naturali Gruppo target
148,000 inhabitants of total 52 settlements plus decision-makers and technical staff of the Directorate, as well as other regional and national stakeholders (such as
other Directorates).
Contesto
The project will be implemented in the upper Tisza area. Tisza is after the Danube one of the two major rivers crossing Hungary, with the majority of its catchment area
in the Ukraine, Slovakia and Romania. The upper Tisza area is the entry point of the Tisza to Hungary from the Ukraine. In recent years, Ukrainian water authorities have consolidated and raised
embankments along their side of the river. This increases the risk of floods downstream in addition to factors such as climate change and other human interventions. In the Tisza river section covered
by this project, water is channelled in a narrow, valley-like area. High quality and accurate information on topography and surface objects is needed to ensure precise flood forecasts and rapid
responses.
Hungarian registration number: SH 2/6 Obiettivi
The goal is to protect the upper region of the Tisza river and downstream areas against floods. The project obtains accurate information on topography and vegetation of
embankments to be able to take appropriate measures in case of floods to avoid damages.
Attività
The project consists of the aerial acquisition of topographical and biomass data with laser, orthophoto and hyper-spectral camera. The data is then processed in a relief
model resp. in a spatial vegetation database before resulting in a modelling scenario of dam failure. This final result will be used to up-date prevention plans in case of floods.
Risultati
The expected results are:
Ulteriori informazioni e documentiLinks esterni
|
Principali dati del progetto
Paese:
Importo del prestito svizzero:
CHF 373'840 Budget globale del progetto:
CHF 439'812 Data di approvazione del progetto:
22.12.2010 Status:
In corso Responsabilità per l'attuazione del progetto:
Contatto svizzero:
Numero del progetto: 7F-06743.01
|