Water Supply Rehabilitation Ózd

The control system for the water supply in the municipality of Ózd is antiquated, and 700 to 800 households are not connected to it. Switzerland intends to change this situation by a project contribution of CHF 7.1 million. The aim is to ensure the same level of service standard in the entire municipality, to improve the water quality, and to reduce maintenance costs.

Tematica / Settore d'intervento
Ambiente e infrastrutture
Infrastrutture di base: Acqua potabile
Gruppo target
The municipality of Ózd, Ózd Water and Canalisation Ltd. as well as the 38‘400 inhabitants of this area.
Contesto
The municipality of Ózd town in partnership with the Ózd Water and Canalisation Ltd, a publicly owned company that operates the drinking water supply, strives to rehabilitate the most critical elements of its water supply infrastructure (network pipes and devices and storage basins). The transportation mains, city mains and household connections suffer from early aging due to poor quality of the pipes, un-thorough execution of the mounting works and insufficient bedding of the pipes. Furthermore the deterioration is accelerated by the aggressive geological conditions.

Hungarian registration number: SH 3/13
Obiettivi
  • To provide the same level of service (security of supply and quality) in the urban area of Ózd.
  • To meet the current EU standards.
  • To enable the water company to cover a part of the maintenance costs from the savings due to this project and also to invest the savings partly into the rehabilitation of the entire network even after this project is implemented.
Attività
Replacement of the most critical parts of the water supply network. Complete renewal of the control system.
Risultati
  • A part of the water supply infrastructure in the city is rehabilitated.
  • In one district, which does not yet have a connection to the central supply, the drinking water network is rebuilt and connects 3'500 people or 700-800 households.
  • The risk of secondary water pollution decreases.

Ulteriori informazioni e documenti


Links esterni
Articoli e Comunicati stampa
Principali dati del progetto
Paese:
Ungheria Ungheria
Importo del prestito svizzero:
CHF 7'165'500
Budget globale del progetto:
CHF 8'430'000
Data di approvazione del progetto:
23.08.2010
Status:
In corso
Responsabilità per l'attuazione del progetto:
Contatto svizzero: